Existing NE 31st Street Bridge:
The existing bridge was built in 1950. It is a two-span structure and each span consists of precast channel girders supported on timber pile caps. Each timber pile cap is supported on five timber piles. The center pier has two piles (middle and adjacent) that have severe rot, diminishing their ability to carry vertical loads. In 2014 temporary vertical supports were installed at the center pier to increase the load carrying capacity until the bridge could be replaced.
New NE 31st Street Bridge:
The new bridge will be a single span structure of 75 feet. The superstructure will consist of precast concrete voided slab girders. The girders will be set on two reinforced concrete abutments. The abutments will be founded on driven pile foundations.
Street Closure for Construction:
Since this project is replacing an existing bridge with a new bridge at the same location, NE 31st Street will be closed while the project is constructed.
Construction:
The construction contract was awarded on April 16, 2018 to Hamilton Construction Co.
Construction Schedule:
Click Here for 3-Week Look Ahead Schedule
Construction starts June 18, 2018. Street closure starts June 27, 2018. Girders arrive no later than Spetember 24, 2018. Based on this girder delivery date, street to be re-opened October 22, 2018. However, girders may arrive sooner. If this occurs, the street will be re-opened sooner. Check this web page for schedule updates.
Construction Photos:
To be posted when construction begins.