Park Avenue North Extension

  • Contractor nameOlson Brothers Excavating, Inc.
  • Completion DateFebruary 19, 2025
Park Ave Intersection Complete

Project Description

The project modified the existing intersection of Park Avenue N/Logan Avenue N/N Southport Drive, establishing a new public roadway extending northward from the intersection. The Park Avenue N extension incorporated sidewalks on both sides and a new grade crossing across the BNSF railroad.

End Result

To provide alternative routes and improve circulation to the Landing and the Southport residential/office development.

Project Status

  • Project award date: February 13, 2023
  • Contractor: Olson Brothers Excavating, Inc.
  • Construction start date: May 1, 2023.
  • Substantial completion date: November 1, 2024
  • Physical completion date: February 19, 2025