New Site Development

Solera_North-Side.jpg

Below is a simplified summary of the land use permit review process. Permit types are generally assigned to a permit process based on a Type I-Type VI scale, with Type I permits requiring the most basic administrative review.

Click the "Review" tab below for a description of development permit types.

Prepare

Research

  • Use the Renton Zoning Code to determine the development standards and what is allowed for your property.
  • Discuss the proposed development informally with the Planning Division before submitting an application.
  • Provide the location of critical areas on the submitted plans.

Be Prepared

  • Ensure all items on the applicable submittal checklist are provided and all application forms are signed.
  • Payment for the application is required once the permit invoice is issued to begin the review process.

Codes

Applications and Forms

Apply

Step 1.Apply for Pre-Application Meeting

All pre-application meeting requests must be submitted online via the online permit portal provided below. A complete application requires a Project Narrative, Site Plan and Vicinity Map. 

Online Permit Portal  What To Submit | How To Submit

Note: Once the Pre-Application meeting is scheduled, a Project Manager will be assigned to your project and will remain involved until its completion.

Step 2.Pre-Submittal Screening

  • A Pre-Submittal screening may be required prior to formal Land Use Review. The screening will be performed electronically via an FTP link that your Project Manager will provide to you.
  • After you upload your submittal documents the Project Manager will review the submittal materials to ensure that requested revisions or missing items have been updated and/or corrected.

Step 3.3.A Determination of Complete Application

If all required submittal items are provided and complete, unless waived by the Project Manager, staff will take in the application for official review. Plan review will not start until the invoice has been paid.

3.B Incomplete Application

If the submittal is deemed incomplete, application will be denied and applicant will receive additional instructions via email.

Review

Step 2. 

Step 3.Public Notice and Comment (14 days)

The city will notify the public of the development application and invite comments from the community.

Step 4.ERC Environmental Determination (If Applicable)

  • Type II Land Use Application
    SEPA Determination will be issued with the Administrative Decision
  • Type III Land Use Application
    SEPA Determination will be issued prior to the Public Hearing

Step 5.ERC Determination 14-Day Appeal Period

  • Type III Land Use Application
    If the SEPA Determination is appealed, the appeal will be heard by the Hearing Examiner at the Public Hearing

Step 6.Public Hearing (Type III Only)

  • Type III Land Use Application
    Staff Report will be provided prior to the Public Hearing.

Step 7.Decision

  • Type I and II Land Use Application
    Administrative Decision issued.
  • Type III Land Use Application
    Hearing Examiner issues Decision.

Step 8.14-Day Appeal Period

 


Time Frame

The average time frame for processing of a Environmental Review varies from 6 to 12 weeks depending on the permit type.

  • Types I and II (Administrative) - 6 to 8 weeks
  • Type III (Hearing Examiner) - 8 to 12 weeks
  • Types IV, V, and VI (City Council) - 12 weeks

Next Steps

Decision Document

Once the Notice of Decision has been received, your entitlement has been approved. It is important to read through and understand any approval conditions and expiration dates.

If approved, what do I do next?

  • Work with the Civil Engineers on your next steps for the civil review.
  • If the scope of work does not require civil review, please work with Permit Technician to submit the associated building permit.